The
Wendy Park Bridge links the Cleveland Foundation Centennial Trail Lake Link to Wendy Park on Whiskey Island and Lake Erie.
Construction Details
- Construction Start: December 2019
- Completion: June 2021
- Contract Amount: $5,624,774.00
- Contractor: Great Lakes Construction Co.
- Project Designer: KS Associates
- Contact: Andy Simons, Project Manager, 216-635-3269 or [email protected]
Updates
Southern bridge section being craned into place
- 6/24/21: Official ribbon cutting held
- 5/17/21: Bridge deck to be poured and final preparation for June ribbon cutting
- 4/19/21: Bridge sections erected
- 3/22/21: Preparation for five separate crane lift sequences to place bridge trusses
- 2/22/21: ​​Finalizing bridge erection schedule with railroad
- 1/25/21: Work on bridge gateway feature design
- 12/28/20: Additional bridge sections received on site for staging
- 11/30/20: Coordination with railroad to schedule bridge erection sequence
- 10/29/20: Completed installation of underground electrical and work to finish wall panels
- 9/21/20: Bridge fabrication underway and forming and pouring forward abutment
- 8/24/20: Construction crane mobilized and settlement period finalized
- 7/27/20: Installed crane pad and pier settlement period underway
- 6/29/20: Excavated and built wall 3 and built rear abutment embankment
- 6/1/20: RediRock walls installed
- 5/18/20: Excavation for retaining walls underway
- 5/4/20: Work continues on forming and pouring bridge piers
- 4/20/20: Piles driven for rear abutment
- 3/23/20: Excavation for bridge piers and abutments
- 2/11/19: Crews set to begin pile driving
- 1/17/20: Full mobilization to begin soon
- 12/30/19: Early site work underway
- 10/17/19: Contract awarded. Construction to begin soon
- 9/16/19: Project advertised; bids due October 7, 2019